Log time on a task

In this article, find the following information:

  • Information on time management
  • Log time on a task
    • Access timelogs
    • The different types of time
    • Log time over a period (day, week, month)
    • Choose time unit: hours or days
    • Visual representation of timelogs
  • Example of time management
  • Log times on multiple tasks/members

Information on time management

To understand how time tracking works in general and in Beesbusy in particular, you can read this article: Understanding time management.

Note 1: To log time on a task, it is mandatory that at least one member is assigned to it.

Log time on a task

Access timelogs

To log time on a task, click on it to display the task detail panel. There are then 2 ways to proceed:

  • Task > Who tab of the task detail: click on “Timelog” next to the name of the relevant user to indicate the times per member.
  • Task > Task detail panel: On the right, click on the “Timelogs” mceclip0.png icon to display the task time management panel. At the bottom of this panel, you can indicate the times for each member by time category. The upper part of the panel is a summary view of the times on the task.

The different types of time

You can add and edit the following information:

  • Initial time: estimated time to complete the task
  • Achieved time: time spent on the task
  • Remaining time: remaining time required to complete the task (or for the member to complete their work)

These different indicators can be modified. The other information are then automatically adjusted according to the modifications made.

  • Total time: completed time added to the remaining time (if indicated), otherwise total of the initial times
  • Planned time:
  • Progress: percentage of progress of the task calculated according to the ratio between the initial time, the time completed and the time remaining

Note 2: You can enter an achieved time without necessarily indicating an initial time.

Note 3: The remaining time and completion can be calculated and modified only if the achieved time is indicated.

Log time over a period (day, week, month)

You can log each member’s time (in hours or days) per day, week or month depending on how you wish to log and track their time.

Task > Who tab of the task detail: click on “Timelog” next to the name of the relevant user to indicate the times per member.

Click on mceclip0.png “Plan a period” then select a period to plan the time (month, week or day). Then select a period or date from the calendar. You visualize the availability of the member in real time thanks to the colored circle which is completed proportionally according to the hours already entered.

mceclip0.png

You can plan multiple time periods. The planned time impacts the duration of the task if applicable.

You find the total of the planned times in the summary line.

Note 4: Remember to compare the total time and the planned time to make sure you have planned the time necessary to complete the task for each member.

Choose time unit: days or hours

By default, if no duration is indicated for a task or if there is no time set for the start and end of the task (see When tab in the task detail panel), the time tracking unit is the day.

To be able to log hours, you must either add a task duration in hours, or add a time to the start and end dates of the task (see When tab in the task details).

You can also see the duration of the task at the very top of the task’s time tracking panel.

For more information on the duration of a task, see this article: Scheduling a task.

Visual representation of timelogs

In the What view of a project, if some time is logged on a task, a time symbol mceclip3.png is displayed.

When you log times on a task, the progress indicator (What tab of the task detail) automatically adjusts to the percentage of progress of the time entry.

In the planning views (When and Who views of a project, multi-project views) you visualize the times planned for the task with a brighter colored area.

mceclip1.png

If the times are exceeded, hatching is added outside the task.

Example of time management

Example: delayed task and calculation of the progress

You estimated 1 hour of workload (Initial time), but you actually spent 2 hours on this task and did only half the work. You can indicate an achieved time of 2 hours. In this case, the completion will automatically indicate 100% but you can add 1 hour of remaining time. The progress will automatically be updated to 50%.

Log time on multiple tasks or multiple members

To log time for several tasks or several members, go to the time tracking reports views. For more information, see the dedicated article: Time tracking displays

General note: The time management features are available in the Enterprise subscription.